In 2004, Shoham handled one of the biggest logistics projects on the island at the time . The logistics for the upgrading of the Vassilikos Power Station .
The main equipment handled were an LP Turbine outer casing 47 tons, a Generator Stator 160 tons and 145 tons and 23 tons tranformers.
Our company handled the discharging for the vessels, the transportation to the site and the positioning at the site.